Sunday 19 October 2014

Rendering and Eaves Lining Finished



After a break work resumed on the rendering with the last two of the large walls done, including the longest window header.

Last two large walls rendered
Small wall around front door finished

With one wall, above the awning on the main pavilion, left to go, bad weather and other commitments meant that  it was several weeks before we could line up a date to get together with Brett the renderer and finish it off. With the date scheduled in it rained the night before and looked like it might not be able to be done. Then it stopped raining overnight. It rained again at about 6am but had stopped by 7am. Brett arrived on site, the sun came out and dried the roof and the decision was made to go ahead. Now with lots of practice the final wall presented no real difficulties, beyond it location above the awning and the need to do both the window headers and the wall in the one day (previously we had left the window header dry for at least a day before doing the wall).

The wall was just finished, and before we had a chance to clean up, a brief thunderstorm rolled in. Most bad weather comes from the south west, which would have not been an issue, but unusually the storm came from the north. The awning protected most of the wall and it only got a few spots of rain on it. Climbing on the wet roof to clean up was tricky, but it was a great relief to have the rendering
finished.

Last wall, above awning, rendered
Internally the finishing touches were also being added with a second coat of Livos Ardvis natural oil to the window reveals and door frames and the installation of the internal cavity sliding doors.

Second coat of oil on window reveals
 In the mean time work continued on the decks. A friend, Elle, and her children visited for the weekend and between the rain and swimming at the beach we squeezed in a half a day of decking, finishing off the narrow deck outside the hallway. Careful selection from the random length decking meant that the decking could be done in single spans. We sanded off the burrs around the screw holes and gave it a coat of Intergrain Natural Decking Oil. As the deck was built by two women and was finished so beautifully we like to call it the "girl deck".

The beautiful "girl deck"
Deck outside the hallway
The following weekend we completed the deck around the corner that joins to the hallway deck. The narrow decks provide a transition between inside and outside, also a nice place to sit and look at the garden (when it is planted, or now just imagine the garden). The design of these decks was influenced by the Japanese "engawa". This deck is yet to have the fascia added and a coat of decking oil.

Deck goes around the corner
Apart from the decks the eaves lining was the other big job remaining. Originally I had wanted to not have any eaves lining and have the roof beams exposed and be able to see the underside of the corrugated roof sheets. Unfortunately, when trying to save money on the framing I did not get timber that was durable enough to be exposed to the weather, some being made of laminated timber. I would also have had difficulty detailing the joint between the wall and the roof. So, the decision was made the have Colorbond fascia and to line the eaves. To minimise the need for painting and maintenance I chose to use corrugated Colorbond for the eaves lining.

Corrugated eaves lining on front pavilion
I chose to run the corrugated sheets parallel to the fascia an fitted the edge of the sheet into the slot at the bottom edge of the Colorbond fascia. I then mitered the corners. This meant quite a bit of cutting of the sheets as the eaves were less than one sheet wide and the awnings were over one sheet wide. Luckily this meant that I could use the offcut from the eaves to make up the extra width needed for the awning lining. I bought some Metabo electric sheers to cut the sheets and they have proved worth the $230 cost.

Electric sheers cutting sheet on angle
The junction between the rendered wall and the corrugated sheet will be covered by an angled flashing and the miter corner by a cover strip, however the change of pitch between the two sections of the front roof may prove a little difficult to finish.

Eave with change of  roof pitch on right
Eaves lining at change of roof pitch
A weekend of two ten hour days of work was put in to finish all the eaves lining so that I could measure up all the exact sizes of the flashings and have them delivered the following weekend. The flashings were made up to go down the wall 25 mm then across the first ridge of the corrugated sheets and feather up along the corrugation. Each eave section was measured separately with different angles required for the top, sides and lower edge of each roof. My measurements were a little too accurate and did not leave a tolerance for the bend and fold down against the wall. This meant that the flashings were a little too long and sat a bit too far across the first ridge of the corrugated sheets, but once they are all installed it is not a detail that anyone but the builder will notice.

Eaves lining finished
Corner flashing put on between wall and eave
The longer awnings had sagged a little and had been temporarily propped up with some timber. This timber had to be removed to finish the eaves lining to the awnings, but I could not measure the exact, tin to tin, measurement for the length of the awning stays until the lining of the roof was installed. Thankfully I was able to e-mail Stainless Steel Worx and within a week they had made up the stays in 5mm stainless cable with turnbuckle to allow it to be tightened. We got three made up to make sure they worked. They were a success and so got a further three made up the following week for the main awning. The stainless steel cables are barely noticeable and it means that there  are no posts coming down from the awning.

Stainless steel awning stay
With the house being nearly finished it was appropriate that we got rid of the piece of reo mesh we had been using as a gate and install a more residential and easier to open gate. I am planning to weld up a decorative gate in the future, but in the meantime some generous neighbors have loaned us some spare farm gates and so the property now has a civillised and easy to open entry.

Front gate

Monday 25 August 2014

More Rendering and Eaves Lining Gets Easier

During the week Brett, from Shoalhaven Cement Rendering, finished rendering more of the walls, so that there is now only one wall left to render, the upper north wall of the main pavilion.

Walls freshly rendered
Last wall on the back pavilion finished
Rendering finished on the eastern side of the house
Front door wall rendered
The threat of rain gave the days work a sense of urgency. Luck was on our side and the rain held off until the eaves lining had been installed on the front pavilion. Careful measuring and more accurate cutting, as well as our previous experience, made it much easier to put up the Colorbond corrugated eaves lining sheets.

Electric snips at work
Eaves lining seen from the front of the house
Eaves lining seen from the south
Along the back of the front pavilion the two roofs at different pitches meet at the gutter, but reach the back wall at different heights. So, the eaves lining was done in two sheets, one for each pitch and we will come up with some sort of flashing to close the gap. The alternative of adjusting the timber so that the Colorbond sheets lined up seemed like too much work as it would have had a flow on effect at the corners.  

North view of the front pavilion
Eaves lining at pitch change
The internal fit out continued with curtains being added as wardrobe doors.

A rainy Sunday was spent cleaning the internal windows and doing a second coat of Livos Ardvos wood oil on the timber reveals on the windows and on the door frames.

Pictures will be posted soon.

Sunday 17 August 2014

Decking Begins

Seven months ago I put in the bearers and joists for the three decks around the house and now, finally, with the help of my friend Martin we have started to lay the decking. Starting on the tricky curved deck first. The decking is locally milled Ironbark from DIY Timbers at Bomaderry. It is a reddish hardwood and I hope it will last a long time.

With longevity in mind we covered the joists with "Protect a  Deck" black plastic stripping to protect the tops of the treated pine joists.  We also made a last minute decision to add a fascia on the outside of the joists. A decision I am pleased we made as it finishes the deck nicely and helped the layout of that section to be completed using whole decking boards.

Joist protection and fascia in place
The radius of the curve meant that some thought had to go into how the last few boards were going to be supported and this required the addition of some extra blocking on the outer edge of some of the joists.

Edge adjusted to be able to support curved deck
The next tricky job was to work out how to space the boards so that they finished nicely against the edge of the deck and against the house. We ended up laying out the boards to see how they would fit. We used some plastic 3.2mm wedges left over from the window installation to space out the boards. The spacing looked good and fitted the required layout.

Boards laid out to determine spacing
The sliding doors were stepped down and set into the slab, this meant that we had to cut a board down to fit around the walls. With care we were able to finish a whole board against the sliding door. The slab also had a few dags of concrete that had to be removed with an angle grinder so that the board closes to the house sat flat against the lip of the slab and the joists.

Decking cut in to fit to sliding doors.
Many of the decking boards were bowed and needed to be persuaded into position with a sash clamp or crowbar wedged into the ground or pried apart with a chisel, and sometimes they the boards just needed a bit of brute force to push them straight. It was a time consuming job as many boards needed straightening along their length for each set of screws to be put in. The decking is held down with 50mm stainless steel square head screws. The screws were bought on e-bay from Fasteners Galore and came with a "Smart Bit" a drill bit with an integrated countersink, a big time saver, as with the hardwood the screws definitely needed to be countersunk.

Sash clamp and chisels used to straighten decking boards
We oiled the edges and underside of the deck with Intergrain Natural Decking oil as we laid them, as these sections will be inaccessible later and i am keen to make this deck last as long as possible. The top of  the deck will be oiled when completed. Work continued until and a little after dark, but we wanted to finish the long section of the deck and were pleased we did.

Deck completed about 6pm
 We left the decking boards long ready to cut off along the curve when the rest of the deck is made.

Deck in the light of day
Beautiful deck to step out onto
After a day's work decking time was taken off building to walk to The Castle in the Budawangs, west of Milton. A steep and challenging hike was worth it for the adventure and the amazing views.

Panorama from the top
View to Pigeon House Mountain


 


Thursday 7 August 2014

Corrugated Eaves Lining and Light Earth Building

During a few weeks off building what does an owner builder do but help someone else build. Some friend hosted a workshop to build their strawbale extension. The extension also used some internal cob walls and external light earth walls. Here I want to comment on the light earth walls as I was considering building the Culburra house from light earth before deciding to build with hemp. The light earth was enjoyable to build with, but for my project I am glad we used hemp. Light earth is made of straw coated in a light slurry of clay, it is packed into a form work and later rendered after the form work was removed. The builder on my friends job had made his own straw cannon to mix the clay and straw mix. This was a great invention, but I prefer the more uniform result of mixing hemp in a pan mixer, the light earth mix we were working with was quite variable. I was told this was not a problem, but as a more precise hemp mixer this troubled me. I could see the benefit of the light earth was that the materials were cheaper than the hemp and lime mix, but it was also a much more labour intensive job. The mixing was more labour intensive and the packing and tamping required much more physical effort and was more time consuming than laying hemp. Because when we were building we had a labour force of two, or three or four if we were lucky, it was more cost effective to use a less labour intensive building. The light earth seemed to go up quickly, but the workshop had a workforce if about 25 on site, plenty of hand to attend to those labour intensive jobs. As a first time owner builder I have also felt reassured that the hemp sets by way of a chemical reaction and I did not have to worry about the walls rotting before they dried out or of potential moisture problems. Hence my preference to use hemp for my particular project.

Light earth walls
Meanwhile back on site, Len and Ben the plumbers were busy at work installing the down pipes, hooking up the remainder if the roofs to the water tank ( for some time only one of three roofs was plumbed to the tank) and installing the storm water overflow pit, as we have no access to stormwater disposal. The water tank is connected to the toilets and washing machine and is also for outdoor watering. The water from three separate roofs runs into the tank, so that the pipers did not go overhead two of the downpipes are charged pipes, meaning that they are full of water up to the level of the tank. The need for charged pipes meant that we had no option but to use PVC. However a lick of paint in Windspray to match the eaves and tank will hopefully take away the plastic look.

Tank plumbed in
I chose to line the eaves with corrugated Colorbond, as reason for this was for ease of maintenance as there is no need to paint Colorbond, and for the look, as with the skillion roofs the underside of the eaves are much more visible than usual. I chose the standard corrugated profile over mini orb, as with the large eaves mini orb would look too busy, plus the standard corrugated sheets are less expensive and more rigid making them easier to put up.

I chose to run the corrugations parallel to each of the walls and miter the corners. The corrugated sheets were wider than the 600mm eaves and I bought some electric sheers to cut down the sheets and also cut the 45 degree angles at the corners. I was so worried that I would cut the metal the wrong way, because I had to think of the eaves lining above you rather than lying on the ground, that it cut the first angle the right way but on the wrong end of the sheet. As I was fitting the corro sheet into the slot in the metal fascia there was only one way the metal could go.

After that disaster the installation of the first sheet did not go particularly well either. I started on the low side of the eaves, thinking it would be easier, but due to the sloped roof the corro had to be pushed in towards the wall then up before being curved slightly to fit it into the slot in the fascia. The corro got stuck too low on part of the wall and when pushing it up pulled off a part if the render. Hopefully thus will be covered by the angle strip that will be put on later or I can just patch it a little.

Eaves lining in Colorbond Windspray
The next sheet was easier as we worked out the need, on the lower side of the roof, to push the corro up and hard against the hemp wall before trying to push it into the fascia. Cutting the metal, holding it above your head and screwing it in at the same time made for some sore arms. To cheer up after a day of mixed success I put up two more of the Japanese rain chains that take the water from the awnings. It was amazing to see how beautiful a functional object could be, and the shadows they cast were an unexpected surprise.
Japanese rain chain to take water from awning gutter
The following day work resumed on the eaves lining. Putting the corro up on the sloped sides of the house required a bit of scaffolding and a different technique. Once in the right place with the mitred corners matching up we put one screw in to hold the sheet, then one person held the other end while the second person fitted it into the fascia slot. On the high side of the roof the manoeuvring if the sheet was slightly different again, but with the fascia supporting one side of the sheet it was amazing that such large sheets of corro could be held up by two screws, more roofing screws being put in place once it no longer had to be held up. Putting up the eaves lining is really a three person job that we have managed to do with two. We now just have to keep going and put up the lining on the other two roofs and the awnings.

Looking up at the eaves
Nicely mitered corners
Working our way around the house
The good thing about the eaves lining us that you don't really notice it whereas you did when the timber was visible. The eaves lining is starting to give the house a real finished look.





Wednesday 6 August 2014

Colorbond Window Sills

The upper windows were taped up ready for rendering, the window header was patched up and ready to go when it became apparent how silly and difficult it would be to render the small patch of hemp between the window and the upturn of the roof flashing. In fact on all other windows the wall forming the sill slopes away from the window, but the wall forming the sill under the upper windows was made flat as it was too difficult to slope the sills when the walls were being made.

Upper windows ready for rendering
Tiny section of hemp between window and roof flashing
The solution was to get out the angle grinder and cut away the hemp wall so that it sloped down from the window to the top of the roof flashing. I then carefully measured the angle, which was slightly different for each window, and ordered some Colorbond angles from Kiteleys Roofing to be made up in the same colour as the roof to slot in under the bottom of the window then go over the roof flashing. The result was a very neat finish and it saved hours of fiddly rendering. I am also very confident that it will not leak.

Hemp wall cut off with an angle grinder
Installed flashing blends seamlessly with roof
Although the outside of the house had been left untended for about a year without any problems it seems that now some birds had decided to try and make a nest in the wall. Luckily they started on a weaker spot where a spacer hole had been filled and the spacer had been over one of the timber studs, which meant the birds were stopped by the stud and did not get all the way through the wall. It just showed us we needed to hurry up with the rendering.

Bird holes in hemp walls
Brett, our renderer was caught up with other jobs, but put in a weekend of work to try and get the walls finished. Significant progress was made with render going on around three of the five upper windows.

Front pavilion completely rendered
Render around upper windows on back pavilion done
 New techniques were also tried out. The hemp making up the window header above the long kitchen window was loose and crumbly, possibly because there was a very thick lintel behind the hemp, which was therefore separated into two parts rather than being able to key in each if the sides together. Screws with plastic washers had been used to try to help the wall stay together but thus did not assist with the crumbly window header. The solution was to mix up a slurry of sand and cement and flick it on the window header, using a special tool for the purpose. The cement helped hold the wall together enough to stop it crumbling, but only covered such a small area it would not affect the breathability of the walls. Once the cement slurry had set it was much easier to patch the gaps ready for rendering. The texture created will also help provide a key for the render to adhere to.

Cement slurry flicked on window header
Holes patched ready for render
The weekend of rendering meant that we only have three walls and the front door area left and the rendering of the whole house will be done. An exciting prospect.

East wall of back pavilion
House looks finished from the back
Render finished on the western side of the house